PMI-ACP is the PMI Agile Certified Practitioner credential. PMI writes the outline; a fail is another sitting fee and a delayed start, not a school-curve disappointment. Related CoStudy banks (pmp, capm) test different sittings — using one as a stand-in for PMI-ACP is how people fail the appointment they paid for.

CoStudy’s PMI-ACP — Agile Certified Practitioner bank holds 166 multiple-choice questions and 100 flashcards. The published material this bank is written against begins: PMI Agile Certified Practitioner (PMI-ACP) Exam Content Outline (public, pmi.org) — 7 domains: 1) Agile Principles and Mindset (16%), 2) Value-Driven Delivery (20%), 3) Stakeholder Engagement (17%), 4) Team Performance (16%), 5) Adaptive Planning (12%), 6) Problem Detection and… Every multiple-choice item on this page shows the full rationale in the HTML. CoStudy is not PMI. We do not have live items, and we do not guarantee a result.

  • 266 total items
  • 166 multiple choice
  • 100 flashcards

Study PMI-ACP — Agile Certified Practitioner in CoStudy →

Exam facts

Copied from the cited official page on the date shown. Rows marked unverified were not confirmed on that pass — check the certifying body before you pay or schedule. CoStudy is not the exam owner.

FactDetailSource
What it isPMI-ACP — Agile Certified Practitioner is administered under PMI. CoStudy is independent practice, not the exam owner. (unverified)PMI public outline · as of 2026-10
Published outlinePMI Agile Certified Practitioner (PMI-ACP) Exam Content Outline (public, pmi.org) — 7 domains: 1) Agile Principles and Mindset (16%), 2) Value-Driven Delivery (20%), 3) Stakeholder Engagement (17%), 4) Team Performance (16%), 5) Adaptive Planning (12%), 6) Problem Detection and Resolution (10%), 7) Continuous Improvement (9%). Covers Scrum, Kanban, Lean, XP, hybrid. 120 questions, 3 hours. MCQs reference public PMI… (unverified)PMI public outline · as of 2026-10
Domain weights (from the outline blurb)Agile Principles and Mindset 16%; Value-Driven Delivery 20%; Stakeholder Engagement 17%; Team Performance 16%; Adaptive Planning 12%; Problem Detection and Resolution 10%; Continuous Improvement 9% (unverified)PMI public outline · as of 2026-10
Passing score / pass rateOnly the certifying body publishes a cut score or pass rate. This page does not invent one. (unverified)PMI public outline · as of 2026-10
Fees and eligibilityApplication, sitting, and retake rules live on PMI’s site and can change. Confirm there before you pay. (unverified)PMI public outline · as of 2026-10

Exam format, sections and weights

Published domain weights from the cited official outline. Re-check the certifying body before you sit — weights move.

SectionPublished weight
Agile Principles and Mindset16%
Value-Driven Delivery20%
Stakeholder Engagement17%
Team Performance16%
Adaptive Planning12%
Problem Detection and Resolution10%
Continuous Improvement9%

How this bank is different

  • PMI-ACP follows a PMI exam content outline. CAPM, PMP, and PMI-ACP are different sittings.
  • Pick the process that fits the constraint in the stem, not the process-group poster you memorised.
  • PMI publishes domain weights on the credential page. Re-check them before you sit — they have moved.

Exam format and blueprint

PMI Agile Certified Practitioner (PMI-ACP) Exam Content Outline (public, pmi.org) — 7 domains: 1) Agile Principles and Mindset (16%), 2) Value-Driven Delivery (20%), 3) Stakeholder Engagement (17%), 4) Team Performance (16%), 5) Adaptive Planning (12%), 6) Problem Detection and Resolution (10%), 7) Continuous Improvement (9%). Covers Scrum, Kanban, Lean, XP, hybrid. 120 questions, 3 hours. MCQs reference public PMI ECO and standard Agile frameworks.

Study timeline

Read the current PMI outline for PMI-ACP before you trust an old domain-weight blog post. Then practise situational items, not posters.

Six-week PMI-ACP block — 10–14 hours/week

Weeks 1–4: mixed practice with an error log. Week 5: only the item types you miss. Week 6: timed full-length sittings. Do not add a second exam’s outline in the last ten days.

Twelve-week working-hours plan — 6–8 hours/week

Two or three evenings and one weekend block. Keep a written error log keyed to chapters, not to “I was tired.” The last fourteen days are timing and weak-chapter repair only. If you are also sitting a related exam (pmp), do not merge the decks.

Free PMI-ACP — Agile Certified Practitioner practice questions

A sample of 12 multiple-choice questions from the bank, with the full rationale shown.

Which is the BEST description of 'value stream mapping'?

  1. Diagramming an org chart
  2. The product roadmap
  3. Visualizing every step from concept to customer delivery, identifying value-add vs. non-value-add (waste) time
  4. The Definition of Done

Answer: C — Visualizing every step from concept to customer delivery, identifying value-add vs. non-value-add (waste) time

VSM (Lean): map end-to-end flow, surface waste. Highlights wait time (often 90%+ of lead time) as primary improvement lever.

Which is the BEST way to make retro action items actually happen?

  1. Capture them in a document and revisit next quarter
  2. Limit to 1-3 items, assign an owner, and add them to the backlog (or working agreement) for the next sprint
  3. Email them to management
  4. Pick the largest items

Answer: B — Limit to 1-3 items, assign an owner, and add them to the backlog (or working agreement) for the next sprint

Action items die from over-commitment + no owner. Few + owned + on backlog → actually done. D is anti-pattern (too big to finish).

What is the CONE OF UNCERTAINTY?

  1. Concept showing that estimation uncertainty is HIGH early in a project and DECREASES as the project progresses and more is learned
  2. A meeting room shape
  3. Pure linear scale
  4. Risk register
  5. Pareto chart

Answer: A — Concept showing that estimation uncertainty is HIGH early in a project and DECREASES as the project progresses and more is learned

Cone of Uncertainty (Boehm): early estimates can be 4x off; converge as work proceeds. Agile embraces this: defer detailed estimation, plan in waves, iterate. Justifies high-level early estimates with finer ones close-in. PMI-ACP planning topic.

Which is the BEST description of a 'Definition of Ready' (DoR)?

  1. Same as DoD
  2. Checklist for backlog items before they enter a sprint — clear, sized, no blockers, acceptance criteria defined — improves predictability
  3. Sprint deadline
  4. Hire criteria
  5. Risk threshold

Answer: B — Checklist for backlog items before they enter a sprint — clear, sized, no blockers, acceptance criteria defined — improves predictability

DoR (vs. DoD): when a story is ready to be picked up. Reduces sprint failure due to under-refined work. Used in many teams. Counterweight to DoD (when done). PMI-ACP Domain 5.

All of the following are ways an agile leader builds psychological safety EXCEPT:

  1. Treating failed experiments as learning opportunities in retrospectives
  2. Inviting quieter members to contribute during team discussions
  3. Modeling vulnerability by admitting their own mistakes
  4. Tracking individual error counts and reviewing them in team meetings

Answer: D — Tracking individual error counts and reviewing them in team meetings

A) Framing failure as learning is a core safety practice. B) Inclusive facilitation increases safety. C) Leader vulnerability signals that candor is safe. D) Correct exception — publicly tracking individual errors creates fear and discourages transparency.

A high-fidelity prototype is MOST appropriate when:

  1. Early in discovery
  2. The customer is unavailable
  3. The team wants to lock scope
  4. Validating final visual details and usability nuances after concept is settled

Answer: D — Validating final visual details and usability nuances after concept is settled

Hi-fi after low-fi. Hi-fi signals 'done' so feedback narrows to nuances. Don't waste effort on hi-fi during concept exploration (A).

Kaizen is BEST described as:

  1. A major reorganization
  2. An annual planning event
  3. Replacing the team
  4. Continuous small improvements driven by the people doing the work

Answer: D — Continuous small improvements driven by the people doing the work

Kaizen (Japanese 'change for better'): small, ongoing, bottom-up. Foundation of Lean continuous improvement. A is the opposite (Kaikaku).

Which is TRUE about agile estimation accuracy improving over time?

  1. Cone of Uncertainty narrows as more is learned — estimates remain ranges but tighten as the project progresses
  2. Estimates become exact
  3. Estimates lose value over time
  4. The team should re-estimate every story every sprint

Answer: A — Cone of Uncertainty narrows as more is learned — estimates remain ranges but tighten as the project progresses

Cone of Uncertainty (McConnell): wide at start, narrow as work proceeds. Estimates are ranges, never points.

Which is the BEST way to handle a TEAM that has plateaued in performance?

  1. Replace team
  2. Add more meetings
  3. Cut estimates
  4. In retros, explore root cause (process, environment, skills, motivation, tech debt); experiment with small changes; measure impact; share learnings across org
  5. Eliminate retros

Answer: D — In retros, explore root cause (process, environment, skills, motivation, tech debt); experiment with small changes; measure impact; share learnings across org

Continuous improvement: retros surface plateaus. Small experiments (one change at a time), measure, share. Often it's environment/process not effort. PMI-ACP Domain 7 (Continuous Improvement).

Speed Leas / Mahler classify conflict on which 5-level scale?

  1. Level 1 Problem to solve → Level 5 World war
  2. Level 1 Disagreement → Level 5 Intractable
  3. Level 1 Mild → Level 5 Severe
  4. Level 1 Friendly → Level 5 Hostile

Answer: A — Level 1 Problem to solve → Level 5 World war

Speed Leas levels: 1) Problem to solve, 2) Disagreement, 3) Contest, 4) Crusade, 5) World war. Used by facilitators to gauge intervention needed.

Which is the BEST approach when a stakeholder requests a new feature mid-sprint?

  1. The Scrum Master adds it to the sprint
  2. The team votes whether to take it on
  3. Route to the Product Owner, who decides whether to add to the Product Backlog and re-prioritize
  4. Refuse all changes during the sprint

Answer: C — Route to the Product Owner, who decides whether to add to the Product Backlog and re-prioritize

PO is single voice for stakeholders re: backlog. Off-by-one role trap (A — SM doesn't own backlog). D is too rigid — change can happen, just via PO.

Planning Poker uses which sequence to discourage false precision in large estimates?

  1. Fibonacci or modified Fibonacci (e.g., 1, 2, 3, 5, 8, 13, 20, 40, 100)
  2. Linear: 1, 2, 3, 4, 5...
  3. Powers of 10
  4. Random

Answer: A — Fibonacci or modified Fibonacci (e.g., 1, 2, 3, 5, 8, 13, 20, 40, 100)

Fibonacci gaps widen with size → acknowledges uncertainty grows with size. Linear (A) implies you can distinguish a 4 from a 5 in a big story.

PMI-ACP — Agile Certified Practitioner flashcards

6 sample cards from the 100 in the bank.

Servant leadership?

Leader serves team. Removes obstacles. Empowers + supports vs commands.

Adaptive planning?

Plan iteratively. Adjust based on learning. Different from upfront waterfall planning.

Product Owner role?

Maximizes product value. Manages product backlog. Single voice for stakeholders.

Resistance to change?

Common. Address with education, leadership support, demonstrating wins.

Sprint Backlog?

Items selected for current sprint + plan to deliver. Owned by Dev Team.

Kaizen?

Continuous incremental improvement. Japanese. Lean origin.

Practise the full PMI-ACP — Agile Certified Practitioner bank

These samples are a small slice. The full bank runs flashcards, multiple choice and timed mock exams with per-chapter progress tracking, on the web and in the iOS app.

Open PMI-ACP — Agile Certified Practitioner →

Frequently asked

What is the PMI-ACP exam?

PMI Agile Certified Practitioner (PMI-ACP) Exam Content Outline (public, pmi.org) — 7 domains: 1) Agile Principles and Mindset (16%), 2) Value-Driven Delivery (20%), 3) Stakeholder Engagement (17%), 4) Team Performance (16%), 5) Adaptive Planning (12%), 6) Problem Detection and Resolution (10%), 7) Continuous Improvement (9%). Covers Scrum, Kanban, Lean, XP, hybrid. 120 questions, 3 hours. MCQs reference public PMI ECO and standard Agile frameworks.

How is CoStudy’s PMI-ACP bank organised?

It holds 266 items (166 multiple-choice, 100 flashcards). Free samples on this page include the full rationale, with no account.

Should I study PMI-ACP and pmp as one pile?

No. PMI-ACP is its own sitting. Related banks on CoStudy (pmp, capm) exist because candidates confuse neighbouring credentials. Use the outline for the exam on your voucher.

Where do PMI-ACP fees, cut scores, and pass rates live?

On PMI’s site. CoStudy will not invent a sitting fee or a pass rate. If a table on this page lacks a citation, treat it as unverified.

Are these real PMI-ACP exam questions?

No. CoStudy does not have live items. The samples below are original practice written to the published outline, with rationales. Anyone selling “real exam dumps” is describing something you should not buy.